Impact of Various Construction Contract Types and Clauses on Project Performance
Publication No
RS5-1
Type
Research & Development Product
Publication Date
Jul 01, 1986
Pages
18
Research Team
RT-005
DOCUMENT DETAILS
Abstract
Key Findings
Filters & Tags
Abstract
Key Findings
The nine most problematic clauses fall into three main groupings: (RS5-1, p. 4)
- Work Scope Clauses – issues involve errors, omissions, ambiguities, and inconsistencies
- Change Clauses – issues involve definitions, dispute resolution, negotiation of costs, and approval timeline
- Project Controls Clauses – issues involve mechanisms to monitor and approve project performance
Contractor and owner views, motivations, and incentives often conflict. Many do coincide, but there is at least potential for conflicting objectives. Contract clauses that do not fit the realities of a situation may promote a conflict of interest. (RS5-1, p. 5)
The type of contract (fixed-cost vs. cost-reimbursable) should be heavily influenced by five factors: (RS5-1, p. 10)
- The extent to which the work is defined
- The desired allocation of risk between owner and contractor
- The availability of owner expertise and effort on the project
- The need to accommodate fast-tracking of design and construction
- The general marketplace conditions
Significant differences were expressed by owners and contractors about those clauses that were most troublesome, and about the risk allocation effect of those particular clauses. There is a prevalent owner practice of using contract language to shift risk to the contractor. There are problems with ambiguity in risk allocation clauses, as evidenced by owners and contractors having different perceptions of the effect of such clauses. Contract preparation that allocates risk with a balanced input from all parties is the most cost-effective. (RS5-1, p. 7)
Filters & Tags
Knowledge Area
Project Phase
Project Function
Industry Group
Research Topic
Contracts
Keywords
Fixed-cost contract,
Cost-reimbursable contract,
Contract clauses,
Allocation of risk,
Incentive plans,
Work scope definition clause,
Change clause,
Project control clause,
Cost effectiveness,
Indemnity,
Consequential damages,
Differing conditions,
Delay
Related Resources
Sign In
Don't have an account? Click here to register for one!
Ready to Become a member?